Remember that we are trying to get the top of the footings and the base of the rail support accurately positioned to within 1/16 of an inch and perfectly leveled with the back of the building five feet away. We actually spent the rest of the day completing that task. We probably would make a good comedy team for a construction gang. We eventually did get everything placed properly and solidly. Here's a couple of pics of the completed footing construction:
This is the west pier. The hammer in the foreground can give a sense of scale. The two steel horizontal beams are temporary and are used to position the frame level in the east-west direction. The two large clamps are also temporary to position the frame level in the north-south direction. The top of the large frame and the wood square are set level with a spot on the north face of the observatory using a laser level. When the cement has set, the wood square on top will be removed. The four bolts it is holding in place will attach to the bottom of the pier supports. The large wood frame will also be unscrewed and removed. The remaiing part of the pit will be backfilled to ground level.
In the above photo you can see down into the excavation pit of the east footing. The pit is 18 inches deep and approximately 3 1/2 feet on a side. There is a rebar grid about 4 inches off the bottom. The entire bottom of the pit will be filled to eight inches of cement covering the bottom rebar grid as well as the second rebar grid that is welded to the vertical rebar. This bottom part of the cement footing will end at the bottom of the large square wood mold. More cement will be poured into the center of the wood mold to the top of the mold and the bottom of the square plate. If you look close at the bottom of the upper right part of the pit you may be able to see a new friend of ours - a 2 inch long stink bug that didn't seem to mind the 40 degree temps all day.
While we were out there another construction team showed up to begin work on preparing the molds for the cement slabs for three more observatories. Here's a shot of them at work excavating and taken from the front of our observatory: They are working under the supervision of a club member who is a contractor. They plan to pour all three slabs on 12/19. Here is the supreme irony that the gods are treating us to. John and I have slaved pretty hard to haul in sixty bags of 60 pound Quikrete - read: 1.8 TONS - to our site and assembled our own portable cement mixer. Why? Because no cement business would come out to our site to pour such a small amount of work - we're five miles up a dirt road from the nearest paved road. We were originally invited and briefly considered joining up with the cement pour for the three new observatories but opted out because they did not plan to pour until spring and that didn't fit our schedule. As of now, we have gone slower and they have gone faster and guess what? On 12/19 when they have the cement truck in to pour the three slabs, we will be mixing our own small pour for our two footings. We could have the truck add a bit more to their mix and pour for us but that meant that we would have to haul out the 60 bags we already have on site.
The gods must be smiling!
On top of that ironic frustration, the weather was mostly overcast, windy, and temps stayed in the lower 40s. The picture below is of an unsual cloud formation called "lenticular". It occurs when strong, straight line winds blow consistently over an elevated area, such as a mountain. In this case this cloud is above the 7,000 foot San Jacinto Mountains on the west side of Palm Springs, about 25 miles to our east.
Below is another shot taken later in the day of a lenticular pancake - several lenticular clouds piled one on top of the other and pretty rare. I have seen that only once before and that was when we lived in New York and that occurred over the Catskills. On the bottom right you can see a water hose snaking off into the distance. That is a 400 foot long set of hoses that I have laid down the last three times we have been working in anticipation of mixing cement.
As we left we were concerned about the weather forecast thru 12/14. According to the So Cal super duper weather men who call a light drizzle a "torrential mist" and interrupt TV programs to warn of an incoming dew front, the desert could get as much as 7 inches of rain from 12/6 thru 12/14. Our estimation that they have their decimal point wrong in the forecast is holding as of today, 12/12 - there has been barely one inch of rain at our desert site.
We will be out there on 12/19, hopefully pouring at least one of the footings. That will end our work for the year.
Here's a fun picture I took from home on Tuesday morning after the first storm cleared out; that's the one that dropped so much snow over so much of the country this past week. This is looking east up my street at the rising sun. Prominent are the crespuscular rays from sunlight piercing through holes in the clouds.
No comments:
Post a Comment