Sunday, April 4, 2010
April 4 + Easter Earthquake
First of all, nobody was injured nor was there any damage from the Easter quake. I'll add more after I update the observatory.
Yesterday both John and I worked at the observatory plus we had a meeting with the club contractor who just completed the other observatories that I've mentioned and shown photos of previously. No pics today - I'll have some next weekend after some more time at the observatory.
We met with Gary, the club contractor, at the observatory yesterday because we are getting a bit tired that our astronomy hobby has been transformed into a building contractor business with the completion seemingly not getting any closer. We are actually almost finished with all but two things: our telescope piers and the roof. We have almost completed all the electrical wiring including the installation of new ceiling lights in the warm room, almost completing the new wall and pocket door. We are half finished with removing the wood molds on our footings that we struggled with over the winter. Unfortunately they will not simply slide up and out of the hole, leaving behind the cement footings. What happened is that wet cement oozed under the forms and encased about three inches of the wood form in concrete. We have had to take a sawzall, squeeze it into the excavated holes, and try to saw thru the forms at an angle. Unexpectedly hard work half done. Then we finally removed the single telescope pier that's in the center of the observing area. I will be re-locating it several feet to one side for my use but we had a surprise, We expected to have one conduit coming up out of the slab to power the telescope. There were three conduits with wires coming out and simply twisted together and a nut slipped over each one - it really should have had a junction box but we finally figured out why three conduits - one came from the main circuit box as expected but the other two conduits run to the two GFI outlets on the outside of the building. Just some more unexpected electrical wring to do.
We met with Gary to see if we can have him help with the roof. After reviewing our autocad drawings and discussing his schedule versus our needs and finances, we will be getting an estimate from him with ten days. He will price it two ways: one - he will complete the entire roof assembly including all of the rail and support work on top of the walls, and two, we will complete the track and support system and Gary will quote only on the roof itself. In both cases, John and I will complete the roof motor mechanism. Hopefully, Gary will be reasonable time-wise (completion by late June) and price-wise (he usually makes nothing on club members and if he under estimates the job, he eats the difference). Meanwhile John and I will continue with the projects we have already initiated, Fortunately, despite the lack of a roof and no permanent piers, the observatory is usable.
You probably have heard about the big quake across the border in Mexico today. Phillis and I were at a friend's house in Huntington Beach sitting down for Easter dinner on his patio when it hit. There were eight of us sitting by the pool when I started to feel a slight side to side motion, minor enough to think it was just my balance. I asked Phil if she felt ti and then it got stronger and everyone felt it. Every quake feels different and this was the most different. It lasted av bout 45 seconds and the motion was a back and forth motion that got fairly strong and then tailed off and then another set of motion with a different period and less strong. When it was over I said it was at least a 7.0 at least a hundred miles away. Just like in the movie "Volcano" - all Californians get into the quick guess before they hear official word. Right now it was a 7.2 almost 140 miles away. This was the first reasonable quake we experienced when it wasn't night and we were outdoors. The pool water sloshed over onto the patio and lost a couple inches of water. It was really cool watching the utility poles swinging back and forth one at a time as each quake wave came thru. I thought the wires were going to snap because they would lose tension and then get very taut every few seconds.
The funny thing was people's reactions. Six of us have felt a number of fairly strong earthquakes so once it was over, talk switched over to talking about past quakes. The two visitors from North Carolina were on the verge of panicking unit they saw how calm we all were. The quake talk went on for about ten minutes and then switched back to other things. When we went inside the TV had a continuous bulletin about the quake but we knew it would be hours before anyone knew anything more than how strong was the quake and where was the epicenter. The visitors were glued to the TV. I was very interested to hear one of the old timers recall when he was ten years old and went thru the Long Beach quake - in 1933!
That's about it until next week.
Thursday, March 11, 2010
March 11


This rut is almost a foot deep and runs all he way to our gate, splitting along the way. The best way to cross this is to try and pass over it at a 90 degree angle - as long as the sides don't collapse!
Here's an axle buster!
Now for the catch-up pics. Here is the outside view with the new stains and weeping from the rain:
East wall:
South wall:
The walls will have to be power washed again prior to painting in a few weeks.
Here is the new door between the warm room and the observing area:

Below is where we replaced the window between the warm room and observing area. This will be covered in a few weeks by the wall from John's warm room.Below is the west footing for the north rail support column, still in its form and not yet back filled:

By next week John will have completed most of the new wiring and I will have completed the new wall. John will also start on his warm room in the current observing area. Within the next month my new camera will arrive and I will start the shake down on my new system. That will get me to the point of coming out for a long weekend where I can work on the observatory, take images and photometry at night, and do afternoon tours at Palomar Observatory, only forty minutes away.
Speaking of which, I was at Palomar last weekend and was snowed on for the first time in California. I got a chance to climb inside part of the telescope. To get an idea of what I'm talking about, here is a standard picture of the Hale telescope at Palomar:


Thursday, March 4, 2010
March 4



Thursday, February 18, 2010
February 12 - 15
We had almost five inches of rain at Anza since my last post. Prior to last weekend we were told by other club members that there was damage to the five mile dirt road to the site and water in the observatory. When we got there it was worse than we expected.
First of all, the road was almost impassable with my Honda Accord. The road is dirt and what is typically called a washboard road. It has many parallel small ridges (an inch or two high) across the road. In my case, driving at 35 mph cancels out the vibration from the washboard. More than 5 mph below or above 35 causes severe vibrations. This time the problem wasn't the washboard road - it was the gullies eroded across the road in random fashion. They were typically about 5 or 6 inches across and up to 2 feet deep. I had to thread my way through a maze of them for most of the way - this part of the drive normally takes 10 minutes; this time it was almost 35 minutes. Slow driving as well as a lot of vibration because of the very slow speed.
Once we got to the observatory we knew that the weekend's work of rewiring the building was out. The outside of the building was a disappointment. Last fall I power washed the outside walls to get rid of the white calcium salts that bled through the cinder block; with the rain, the stains are back and I will have to power wash it again before we paint it when the weather gets warmer.
There were a couple of good things. The wall section replacement for the warm room window that I installed before the rains did not leak and held up well. Also, I did some excavating over the last few months on the top of the slope on the north side of the observatory. I built a berm with the soil removed from the post holes and also dug a trench behind it to draw rain water off to the west around the observatory. That worked very well also.
Remember that the observing area roof is not there yet. Not having a roof can cause problems with rain getting in - duh! What happened was that the rain that fell in the observing area ran down the stairs, through the old warped wooden door and into the warm room. Once the water got into the warm room, it drained only slowly out beneath the outside door. When we got there the floor was wet but not flooded. Fortunately, we had anticipated the possibility of flooding so everything was up on blocks but we still lost some bags of Quikrete - the water must have maxed out at about 5 inches deep. However, the place was like a hothouse - it must have been 100% humidity. The walls were dripping wet and the hanging ceiling panels were soggy and drooping. We always wondered why the ceiling tiles drooped because the roof above the warm room has never leaked. Now we know.
We set a fan blowing on exhaust in the door to clear out the humidity while John and I sat down and strategized about what to do. Obviously, the rewiring work we had planned was down the drain for the time being. The issue was that the new roll-off observing room roof was not going to be on for another several months at least and our rainy season still has a couple of months to go. We needed to find a way to keep the warm room from flooding because that's where most of our immediate work is planned. We were also limited in our choices by whatever materials we currently had on site.
We decided to prevent the warm room from flooding again. First of all we drilled some weep holes in the observing area at the slab level so much of the rain water would go through the walls instead of down the stairs. Then we drilled some additional weep holes at the bottom of the stairs so that whatever water did come down the stairs would drain out that way. The water barrier between the stairs and the warm room is what we spent the rest of the day working on - a brand new external door to replace the warped fiber board inside door that had been there for twenty years.
We needed to rip out the entire frame around the door because the wood was warped and rotten and the door would not close. We built a new door way and fitted the new frame in. We made a perfect fit and the door opened and closed perfectly. We caulked around the door frame especially on the floor and under the new sill. To test the barrier, we poured a couple of buckets of water down the stairs and it flowed out the weep holes and nothing came in under the door. As long as the water by the stairs doesn't top the sill at about an inch we should be okay. I spent some time ripping down all of the old ceiling tiles so John had easy access to the overhead wiring for Sunday. He also set up a temporary telescope pier where his permanent one will be so he can start using the observatory. I'll be setting up within the next month or two.
By the end of the next day, the warm room was pretty dry and John was able to complete about 75% of the rewiring job. He actually had a rough time at Anza those three days. The site well pump died on Thursday and we were without water the entire time.
Next week I will be building a wall with a pocket door across the warm room. One room will be for sleeping and have a desk; the other will have my control area and room for a flat screen TV and coffee nook. John will begin the construction of his personal warm room in the observing area. The only major construction remaining at after that is pouring our two permanent telescope pier footings and building the roll-off roof - probably the two biggest projects.
Saturday, January 16, 2010
January 16






I am hoping for a break before the next set of storms next week and a quick repair to the washed out roads. I'd like to start the rewiring project and get that done in one day. Once that is complete I can build the new dividing wall in the warm room that will make it two smaller rooms - one would be my control room and TV area, plus a small sleeping area.
Saturday, December 19, 2009
December 19
Pouring the slabs down the hill from us.
By the time John showed up I had already laid out the four hundred feet of hose and set up the cement mixer. We spent a bit more time taking the tarps off the footings and once again vacuuming out the two footings holes - probably twenty pounds of loose material that blew in over the last two weeks.
Once we started we realized several things. The cement mixer was Chinese and it did work - barely. Once we dumped the water and three bags of Quikrete in and started mixing, we found that the baffles in the mixer were not well designed and did not mix the material in the bottom of the mixer. We had to stop every few minutes and hand mix the bottom stuff to get it uniform. I should have known with my previous experience with Chinese equipment that they are barely functional if they work at all - you get exactly what you pay for.
We also realized that because of the height of the top of the mixer that only I could load the 60 pound bags of Quikrete into the mixer - I had to lift the bag almost to shoulder height and then flip it over and onto the top of the mixer. We got through the first twelve bags, or 720 pounds of cement, pretty quick with me mixing, John and I sharing the transport to the footing holes by wheel barrel. Then John shoveled the cement into the footings and his wife worked the cement to fill in vacant pockets, all while I mixed another load.
Then we found out that the gods approved of our light hearted acceptance of their trick upon us the other week. The club contractor, who was directing the pours for the other observatories, came over and said that they were finished and did we want the remaining cement for nothing - about a cubic yard by his estimation. We of course said yes and the last cement truck pulled as far up our driveway as possible. The cement was dumped into our wheel barrel and we wheeled it over to our work area. We got a total of eight wheel barrels out of the truck and that turned out to be a bit more than we needed. John taking a barrel of cement from the truck.
This was great! What we figured to be an all day job finished by noon. Of course now we have 48 remaining bags (1.4 TONS) of Quikrete that we have no current plans for but we do have some future plans. We are thinking of building a totally enclosed BBQ pit off the south side of the observatory. Also, we are thinking of building a pad for visual observing off of our south-east corner; it would include a small shed that would roll on rails set into the pad and would house my sixteen inch Dob reflector that has been mothballed for the last five years.
John and his wife working on the initial smoothing after the pour was complete on the west footing.

John rough smoothing the surface of the west footing.
Today was the first time that we finished a days' work ahead of schedule so after we had lunch and basked in the 70 degree sunny weather for awhile, we walked around the site to see the other pads that were poured today. Tonight is the club's monthly star party so there were quite a few people starting to show up by mid-afternoon. One of the old timers said that today saw more construction at our site than has ever occurred previously in a single day.


Here are two of the new slabs poured today. They are the ones from the first picture that showed the cement truck at work.

Saturday, December 12, 2009
December 5
Remember that we are trying to get the top of the footings and the base of the rail support accurately positioned to within 1/16 of an inch and perfectly leveled with the back of the building five feet away. We actually spent the rest of the day completing that task. We probably would make a good comedy team for a construction gang. We eventually did get everything placed properly and solidly. Here's a couple of pics of the completed footing construction:
While we were out there another construction team showed up to begin work on preparing the molds for the cement slabs for three more observatories. Here's a shot of them at work excavating and taken from the front of our observatory: They are working under the supervision of a club member who is a contractor. They plan to pour all three slabs on 12/19. Here is the supreme irony that the gods are treating us to. John and I have slaved pretty hard to haul in sixty bags of 60 pound Quikrete - read: 1.8 TONS - to our site and assembled our own portable cement mixer. Why? Because no cement business would come out to our site to pour such a small amount of work - we're five miles up a dirt road from the nearest paved road. We were originally invited and briefly considered joining up with the cement pour for the three new observatories but opted out because they did not plan to pour until spring and that didn't fit our schedule. As of now, we have gone slower and they have gone faster and guess what? On 12/19 when they have the cement truck in to pour the three slabs, we will be mixing our own small pour for our two footings. We could have the truck add a bit more to their mix and pour for us but that meant that we would have to haul out the 60 bags we already have on site.
The gods must be smiling!
On top of that ironic frustration, the weather was mostly overcast, windy, and temps stayed in the lower 40s. The picture below is of an unsual cloud formation called "lenticular". It occurs when strong, straight line winds blow consistently over an elevated area, such as a mountain. In this case this cloud is above the 7,000 foot San Jacinto Mountains on the west side of Palm Springs, about 25 miles to our east.
Below is another shot taken later in the day of a lenticular pancake - several lenticular clouds piled one on top of the other and pretty rare. I have seen that only once before and that was when we lived in New York and that occurred over the Catskills. On the bottom right you can see a water hose snaking off into the distance. That is a 400 foot long set of hoses that I have laid down the last three times we have been working in anticipation of mixing cement. As we left we were concerned about the weather forecast thru 12/14. According to the So Cal super duper weather men who call a light drizzle a "torrential mist" and interrupt TV programs to warn of an incoming dew front, the desert could get as much as 7 inches of rain from 12/6 thru 12/14. Our estimation that they have their decimal point wrong in the forecast is holding as of today, 12/12 - there has been barely one inch of rain at our desert site.
We will be out there on 12/19, hopefully pouring at least one of the footings. That will end our work for the year.
Here's a fun picture I took from home on Tuesday morning after the first storm cleared out; that's the one that dropped so much snow over so much of the country this past week. This is looking east up my street at the rising sun. Prominent are the crespuscular rays from sunlight piercing through holes in the clouds.